Fence Project Updated, March 2009:

We are ready for the concrete after passing the tied-beam inspection on March 5, 2009.

Our concrete-block walls are in place. Many thanks to Mr. Dave for his given cement blocks! We have used them all! In order to further finish our fence, we will need to add the steel beams, pump the concrete, and put on a layer of stucco.

The footing for the fence, both in the back and front, is finished. The weather is cold again. Hoping that the usually warm sunshine will soon return. Everything is in progress.

We are looking forward to finishing our the masonry walls. And then the aluminum gates will follow.

We are working on making our office at 621 S. Federal Hwy, Lake Worth.

Again, here are a few photos of our progress.

 

The fence is up!

As of March 24, 2009.

The fence in front, March 5, 2009.

Facing the morning sun !

A front view on March 2, 2009, a cold day!

Before, in mid-February!

Now, the fence is up along Federal Hwy!

Inside of the fence in front!

The fence in the back!

A wall really! Ready for another inspection!

The back fence: Another view! ( March 5, 2009)

Progress since March 2, 2009:

Constructors in action!

Good management!

Mr. David and his team at work!

Keep them straight!

Need more mud !

Nearly done! We used up all the blocks given by Mr. David!

The concrete truck! February 22, 2009.

For the back wall, near the end!

After finishing the footing! (February 27, 2009)

Then comes the back wall! (March 2, 2009)

The wall in the back and...more work!

 

And the usual views of our place.

A front view of our future office.

Across from Federal Hwy.

And of course, there is peace!